A formal investigation has determined that the City of Winnipeg paid $43.3 million too much for its downtown police headquarters. The findings also implicate former mayor Sam Katz and former CAO Phil Sheegl in conflict-of-interest breaches.

Advertisement

The $43.3 Million Overcharge at the Canada Post Building

The final report from the police headquarters inquiry concludes that the City of Winnipeg was overcharged by $43.3 million during the development of its downtown station. According to the report , the total cost for the project—which involved the acquisition and renovation of the foormer Canada Post building—reached $209 million. This massive overpayment was not a simple accounting error but was driven by financial misrepresentations made by the owners of Caspian Construction and their various subcontractors.

The scale of the overcharge highlights a significant failure in the city's financial oversight. By allowing Caspian Construction to misrepresent costs, the City of Winnipeg effectively subsidized a project far beyond its actual value, leaving taxpayers to foot a bill that was tens of millions of dollars higher than necessary .

The $327,000 Arizona Land Deal Controversy

At the heart of the scandal is a $327,000 payment made by Armik Babakhanians, the owner of Caspian Construction, to former mayor Sam Katz and former CAO Phil Sheegl. While both Katz and Sheegl testified that this money was tied to a separate land transaction in Arizona, Commissioner Garth Smorang found the timing of the payment to be highly suspicious. The report notes that these funds were transferred while Sam Katz was actively voting on motions to increase the budget for the police headquarters project.

Commissioner Smorang stated that the conflicts of interest were so blatant that they will always be questioned, regardless of whether a legitimate land deal existed. Furthermore, the inquiry found that Armik Babakhanians engaged in unethical conduct by sending the money to the city's top officials while his company was benefiting from a massive municipal contract. This creates a narrative of "pay-to-play" that undermines the integrity of Winnipeg's municipal governance.

How the $2.1 Million Inquiry Exposes Winnipeg's Procurement Gaps

The inquiry, which cost $2.1 million and spanned four months, suggests that the City of Winnipeg's procurement process was fundamentally flawed. To prevent future failures, Commissioner Smorang recommended that the city employ professional lawyers to draft request for proposal (RFP) documents for all large-scale projects . This would move the technical specifications and legal safeguards away from political influence and into the hands of legal experts.

Beyond the paperwork, the report calls for a systemic overhaul of the mayor's executive policy committee (EPC). Smorang recommended that the Manitoba government review how councillors are appointed to the EPC and how the committee provides oversight. This suggests that the current structure of the EPC may be too insulated or susceptible to the influence of a single powerful mayor, as seen during the tenure of Sam Katz.

Will the City of Winnipeg Recover the Missing Millions?

Despite the clear findings of overpayment, a critical question remains:will the City of Winnipeg actually pursue the $43.3 million? As CTV News reported, the city has not yet indicated whether it intends to act on the inquiry's recommendations or seek legal recovery of the funds from Caspian Construction and its subcontractors.

The silence from current city officials leaves a void in accountability. Without a clear plan to claw back the overcharged funds, the $43.3 million loss becomes a permanent tax burden. Furthermore, it remains to be seen if the Manitoba government will implement the suggested changes to the EPC's makeup to ensure that no future CAO or mayor can operate under such blatant conflicts of interest.